Project planning7 min read

How Long Does It Take to Build a Small Business Website?

Published By Ichii GmbH

Contents
  1. What drives the duration
  2. What typically causes delays
  3. Worked example: same site, two timelines
  4. Plan backwards from your date
  5. Checklist: what to prepare before the first call
  6. After launch: the second clock
  7. How this works at Ichii
  8. When faster is realistic
  9. Your next step

There is no honest single number for how long a small business website takes. What can be said is this: for a site of up to ten pages, the build itself is rarely the bottleneck. Whether the project takes a few weeks or several months depends mainly on three things on your side: when the content is finished, how quickly decisions are made, and whether legal pages and domain access are ready in time.

There is also a second clock that people forget. Once the site is live it can be reached, but Google says crawling new pages can take anywhere from a few days to a few weeks. If you need to be found by an opening date, a trade fair or a funding deadline, plan for that gap.

For founders setting up in Germany, a few extra items tend to stretch the timeline: German text that hasn't been written yet, Impressum details that depend on a company registration still in progress, and a domain registered by someone who is hard to reach.

In short

  • There is no reliable standard duration. It depends on pages, features, languages and, above all, how ready your content is.
  • The most common delays sit with the client: unfinished text, scattered feedback, missing domain access, late legal pages, a second language "running alongside".
  • The clock for a first draft sensibly starts only when content is complete and the scope is confirmed.
  • Search visibility comes on top: crawling can take days to weeks, and changes can take hours to months to show.

What drives the duration

The order of steps is much the same with every provider; it is described in how a website project works. This section is only about what makes each part shorter or longer.

FactorFaster when …Slower when …
Number of pagesfew, clearly defined pagesmany pages, or the list grows mid-project
Textfinal, approved, sorted by pagestill to be written or agreed by several people
Languagesone languagea second language whose text doesn't exist yet
Imagesown photos in good quality, rights clearedphoto shoot still to be booked, rights unclear
Designbuilt on an existing design systemcustom design with several concept rounds
Featurescontact form, map, links to existing toolsbooking, logins, shop or connections to other systems
Decisionsone person approvesseveral people, feedback in instalments
Relaunchnew site with no predecessorold addresses have to be redirected

Treat the middle column as a planning aid rather than a wish list. Every item you move into it before the start takes uncertainty out of the schedule.

What typically causes delays

The table below describes common patterns, not measured averages. It shows when a delay usually becomes visible and what you can do beforehand.

DelayWhen it shows upWhat you can do beforehand
Text is "almost done"at the first draft: pages stay empty or full of placeholderswrite the text before ordering, or commission a copywriter
German version not startedat the draft, or after the English site is livebrief a translator before the build begins
Feedback arrives in instalmentsduring the correction roundname one approver and send changes as one list
New pages are addedafter the first draftfix the page list before confirming the scope
Photos are missing or too smallat the first draftbook the shoot before the project starts
Domain access is missingjust before launchcheck your registrar login now
Impressum and privacy policy are missingjust before launchcollect the details and decide who writes the texts
Cookie or tracking consent is unresolvedjust before launchdecide whether you need analytics or embeds; if they store or read data on visitors' devices, § 25 TDDDG generally requires consent

What matters for the schedule: § 5 DDG requires the Impressum to be permanently available, and Art. 13 GDPR requires you to inform people at the moment a form collects their data. Neither text can follow a week after launch; both have to be live on the first public day.

Your developer usually doesn't write these. If someone only starts on a generator or contacts a lawyer in the last week, the launch moves. One more point for new companies: if your company registration is still in progress, details such as the register number may not exist yet. Ask your adviser how to handle the Impressum in the meantime, and settle it in week one rather than launch week.

Worked example: same site, two timelines

Example

Hypothetical example: an eight-page consultancy site

The business and all durations are invented for illustration. They are not a promise and not an average.

PhaseVersion A: content readyVersion B: content written alongside
First call to complete materials1 week6 weeks (English written in parallel, German translation afterwards)
Scope confirmed in writing2 days1 week (two pages added)
First draft1–2 weeks1–2 weeks
Feedback and corrections1 week3 weeks (two co-founders send separate feedback)
Domain, legal pages, launch2 days2 weeks (domain held by a former agency)
Total (rounded)about 4 weeksabout 13 weeks

The draft takes the same time in both versions. The difference of around two months comes entirely from what happens before and after the build.

Plan backwards from your date

If there is a fixed date, plan back from it rather than forward from the start.

  1. Set a buffer: aim to launch a few weeks before the event itself, so Google has time to crawl and you can fix mistakes calmly.
  2. Subtract launch preparation: domain switch, legal pages and final tests take a few days, much longer if nobody has the domain login.
  3. Subtract the correction round: count your own review time, not just the provider's.
  4. Subtract the first draft: ask the provider how long they need once materials are complete.
  5. Subtract content: usually the biggest block. If the text doesn't exist yet, this is where your project really starts.

If the result lands in the past, you have two options: reduce the scope (launch the essential pages first, add the rest later) or move the date. To decide which pages are essential for a first launch, see which pages a small business website needs.

Checklist: what to prepare before the first call

  • a page list with the planned number of pages
  • text for the home page and the main service pages
  • a decision on languages, and who writes or checks the German text
  • photos you have the rights to use
  • your logo as a vector file
  • Impressum details (name, address, legal form, representatives, register, VAT ID)
  • a decision on who writes the privacy policy
  • a tested login for your domain
  • one named person who approves content
  • your target date, and whether it is fixed or flexible

To collect all of this in one document, use our website brief template.

After launch: the second clock

Live doesn't mean found. Google says crawling new or changed pages can take from a few days to a few weeks, and that asking for a crawl does not guarantee inclusion in search results. Its SEO Starter Guide adds that some changes take effect within hours while others can take several months.

On a relaunch with new addresses, Google also warns that rankings may fluctuate while the site is recrawled, and that for a medium-sized site it can take a few weeks or more before new URLs show up. That is another reason for the buffer before a fixed date.

How this works at Ichii

With our business website package, the clock starts exactly where the example above starts it: you receive the first draft within 7 business days once all materials are in and the scope is confirmed in writing. One correction round and the launch follow. The 7 days are not a launch guarantee; whether your project looks more like Version A or B depends mainly on your text, images, feedback and domain access. The full process is on our site.

When faster is realistic

For a simple site with a few pages, a website builder can be the quickest route if you have the time to do it yourself. The time needed for text, photos, the Impressum and the privacy policy stays the same, though, whoever builds the site.

Your next step

Go through the checklist above. If you can tick most items and your site will have up to 10 pages, a short timeline is realistic. Have a look at our business website offer and send a short enquiry with your target date.

Sources

  1. Ask Google to recrawl your URLs — Google Search Central, accessed 2026-10-09
  2. SEO Starter Guide — Google Search Central, accessed 2026-10-09
  3. Site moves with URL changes — Google Search Central, accessed 2026-10-09
  4. § 5 DDG – Allgemeine Informationspflichten — German Federal Ministry of Justice, gesetze-im-internet.de, accessed 2026-10-09
  5. Art. 13 GDPR – Information to be provided where personal data are collected — dsgvo-gesetz.de (unofficial consolidated text), accessed 2026-10-09
  6. § 25 TDDDG – Protection of privacy in terminal equipment — German Federal Ministry of Justice, gesetze-im-internet.de, accessed 2026-10-09

A business website with up to 10 pages

A one-time €790 net – built on a proven design system with your text and images. The offer page lists everything that is included.

See the website offer